Project 2012 Update - January 21, 2008
Phase I: 2006-2009
- Hepburn Plaza
- Community Health Center & Dental Clinic - Complete
- MVH
- Outpatient Rehab - Complete
- SNU Family Gathering - In design
- DPH - Cancer Center - In process
- TWH
- Property Acquisition - 90% complete (one eminent domain)
- Central Utility Plant - In design, begin in Spring 2008
- Child Day Care Center - In design, begin in Spring 2008
- Gateway Entrance - In design
- Parking - 75% Complete
- Additional Security - 4.5 FTEs added January 2008
Phase II: 2009-2012
- MVH - Inpatient Rooms, Family Visitation Center
- DPH - Replace Convent
- TWH
- Emergency Services
- Surgical Services
- OB
- Imaging Services
- Cardiovascular
- Patient Tower/Private Rooms
Phase III: 2012-2015
- MVH - Parking
- TWH
- Rehabilitation Services
- Patient Parking Deck
- Final Parking Lot Development
|
Background
Project Goals
Schedule
Financing
Frequently Asked Questions
Facility Update Newsletter
|